Centrifugal Pump Bearing Replacement: Key QA/QC Procedures Explained

by | Articles, Bearings, Pumps

Centrifugal pumps are critical components in various industrial sectors, including the oil and gas industry, chemical processing, and marine transport. Their reliability directly impacts operational efficiency and safety.

One of the most common maintenance activities for these pumps is bearing replacement, which, if improperly performed, can lead to premature failures, unscheduled downtime, and costly repairs. Therefore, implementing robust Quality Assurance (QA) and Quality Control (QC) procedures during bearing replacement is essential to ensure mechanical integrity, equipment reliability, and long-term performance.

This article outlines the QA/QC processes and best practices to follow during the replacement of centrifugal pump bearings.

1. Pre-Maintenance QA/QC Planning

a. Review of Documentation

Before the replacement work begins, QA/QC personnel must ensure that all relevant documents are reviewed:

  • Pump maintenance manual
  • OEM bearing specifications
  • Engineering change records
  • Past maintenance history
  • Work permits and safety procedures

b. Job Safety Analysis (JSA)

A JSA must be developed to identify and mitigate risks associated with disassembly, lifting, bearing removal, and reinstallation. QA/QC should confirm that all tools and lifting equipment are certified and calibrated.

2. Bearing Removal – QA/QC Steps

a. Visual and Dimensional Inspection

Before removing the old bearing:

  • Inspect for signs of oil leakage, vibration damage, or unusual wear.
  • Record axial and radial clearances using calibrated tools.
  • Capture photos for documentation and comparison.

Figure 1

b. Controlled Disassembly

QA/QC should ensure:

  • Correct disassembly sequence is followed.
  • Bearing housing, shaft, and other components are protected during removal.
  • Old bearings are retained for failure analysis if needed.

3. Inspection of Pump Components

Once the bearing is removed, QA/QC must conduct:

a. Shaft Inspection

  • Visual Check: For scoring, pitting, or discoloration.
  • Dimensional Check: Verify shaft diameter against tolerances using micrometers.

Runout Check: Ensure shaft runout is within OEM limits using a dial indicator.

Figure 2

b. Housing and Seal Inspection

  • Inspect bearing housing for wear, cracks, or alignment issues.
  • Check mechanical seals and replace if necessary.
  • Ensure fitment surfaces are clean, flat, and burr-free.

4. New Bearing Installation – QA/QC Controls

a. Bearing Verification

QA/QC must verify that the replacement bearing:

  • Matches original equipment manufacturer (OEM) part number and specifications.
  • Is free of corrosion, damage, or packaging defects.
  • Comes with proper material certificates (e.g., MTC or COC).

b. Controlled Installation

  • Use proper tools (hydraulic press, induction heater, etc.) to avoid damage.
  • Ensure the bearing is installed square and seated fully.

Record temperature and time if heat fitting is used.

Figure 3

c. Lubrication Checks

  • Confirm the correct type and amount of lubricant (oil or grease) per OEM guidelines.
  • Ensure bearing and housing are free of contaminants before lubrication.

5. Post-Installation QA/QC

a. Alignment and Tolerances

  • Re-check shaft alignment and bearing clearances after installation.
  • Use laser or dial alignment tools as applicable.
  • Ensure coupling alignment between motor and pump is within tolerance.

b. Functional Testing

  • Conduct no-load and load testing to verify proper operation.
  • Monitor for abnormal noise, vibration, or temperature rise.
  • Record vibration and temperature baseline readings.

c. Documentation and Sign-Off

QA/QC must ensure:

  • All checklists and inspection reports are completed.
  • Test results, photos, and instrument calibration records are archived.
  • Final sign-off is obtained from responsible engineers and inspectors.

6. Common QA/QC Issues to Watch

Table 1

Conclusion

Proper QA/QC procedures during shipping pump bearing replacement are not optional – they are essential. From pre-planning and inspection to installation and final testing, each step must be governed by rigorous standards and verified by qualified personnel. When executed correctly, these measures not only extend the pump’s service life but also enhance overall plant safety and reliability.

Note: For optimal results, it is recommended to tailor the QA/QC process to site-specific standards (e.g., ISO, API, or company SOPs) and to always refer to the OEM documentation.

Author

  • Ibrahim Almatrood

    Ibrahim Almatrood is a Senior Mechanical Quality Technician working as mechanical QC with Reliability unit, Maintenance division. Ibrahim has joined Saudi Aramco since 2006 and his experience in field, workshops and technical technologies is more than 18 years. Ebrahim is certified as Ultrasound Inspector Level 1 and he has certification of certified maintenance and reliability technician (CMRT) through SMRP organization. Ibrahim is a member of Gulf Society for Maintenance and Reliability (GSMR) and he is a member of Society of Maintenance & Reliability Professionals. HE has several technical articles inside Aramco like E-zine magazine and outside Aramco such as maintenance world magazine and Turbomachinery magazine.