How to Measure and Improve Wrench Time

How to Measure and Improve Wrench Time

What Is Wrench Time?

Wrench time is the percentage of a technician's paid on-the-clock time that is spent actually doing direct maintenance (including troubleshooting and diagnosis) under the documented activity categories. It's also known as tool time and is the proportion of a given period spent on direct maintenance, regardless of whether the technician is holding a tool at that moment.

The Society for Maintenance and Reliability Professionals (SMRP) definition of wrench time, revised August 12, 2015, includes both the physical effort and the troubleshooting. It's also very clear that the metric doesn't measure work quality. A good wrench time study will tell you what enables the maintenance technician to work and what impedes them.

What counts as wrench time

Keep three separate clocks. Direct maintenance time is the measure of classified activity. Labor charged to a work order can also include preparation, travel, and waiting. The elapsed time between opening and closing of that work order can include overnight hours or days when no one is on it.

If two techs repair a pump together for two hours, they put in four labor hours of direct maintenance. The repair takes two hours, but the labor hours have to be calculated at four. A work order left open until Friday doesn't tell you how either person spent the time in between.

The percentage alone won't tell you whether the repair fixed the problem, prevented a further failure, or addressed the right piece of equipment. This guide gives you a consistent way of calculating it, a practical way of observing it, and a way of turning verified delays into something the crew can actually assess.

What Counts as Wrench Time?

Table A is the illustrative study codebook which is used throughout this guide. It sets out a consistent convention for the calculations and examples; individual plants and other references may classify activities in different ways.

Direct Maintenance Work

Direct maintenance includes repair, installation, preventive maintenance inspections, testing, calibration, and active troubleshooting. A mechanic measuring shaft alignment after replacing a coupling is performing direct maintenance. So is an electrician comparing drive fault readings to a schematic to determine why a conveyor has been intermittently shutting down.

The activity's purpose determines how it is classified. The observer needs to be assessing whether the technician is actually looking at the evidence, testing a potential cause, or interpreting information in order to make progress with the diagnosis. One person may be doing direct maintenance simply by looking at a drawing. Another person may be waiting for a supervisor to tell them what to do.

Agree on these distinctions during the pilot. If an observer is unable to establish the activity without interrupting the task, then it is to be marked as uncertain and the classification question dealt with at a later stage. Don't assume that a stationary technician is just sitting idle.

Necessary Support and Avoidable Delays

Safety controls, the preparation, the paid training, and the requisite paperwork all contribute to successful maintenance even if they're not in the numerator. Paid breaks are still part of the covered paid period. Coding these activities separately doesn't make them expendable.

For covered work, adhere to the Occupational Safety and Health Administration's (OSHA) hazardous energy control requirements. The performance of lockout/tagout (LOTO) is the support function under this guide's convention. Time spent waiting for equipment to be released or for coordination to be complete falls into the delay category to investigate. Reducing that waiting must of course preserve the required controls.

Table A Activity Categories Used in This Guide

Code

Observed activity

Treatment in this example

D

Direct repair, installation, inspection, testing, calibration, or active troubleshooting

Count in numerator and paid-time denominator

S

Required safety controls, preparation, ordinary travel, coordination, paperwork, or paid training

Support; denominator only

P

Waiting for parts or tools

Delay to investigate; denominator only

A

Waiting because access or required approvals are not ready

Delay to investigate; distinguish from doing safety work

I

Waiting for assignment or instructions

Delay to investigate; denominator only

B

Paid breaks and personal time

Separate paid-time category; denominator only

Use one activity code per valid observation. Keep ordinary travel time in support. If you have a missing gasket, then record that as a secondary reason for an unnecessary return trip and go on to investigate why that happened. Report any unobserved or uncertain activity separately rather than shoehorning it into a category.

Set the Rules Before Comparing Results

Doc Palmer talks about a wider convention whereby LOTO assistance and job paperwork can be credited as wrench time. Those activities are coded as support in this guide. Both conventions can produce internally consistent results; the percentages aren't directly comparable.

Publish the codebook with the study. Keep the activity definitions and paid time boundaries the same across rounds. If you do change an activity definition, then you need to explain the change and establish a comparable baseline before you can make any claim of improvement. Otherwise, a revised coding rule can look like it's increased wrench time when in fact the workday hasn't changed at all.

How to Calculate Wrench Time

Calculate Wrench Time From Hours

The wrench time calculation from classified hours is:

Wrench time percentage = direct maintenance hours ÷ eligible paid on-the-clock hours × 100

A tech who does 2.8 direct maintenance hours in 8 paid hours has 35% wrench time (2.8 ÷ 8 × 100). If the day contains a 30-minute unpaid lunch, then this example is 8 paid hours plus that lunch. The 30-minute unpaid lunch is outside the denominator.

Include paid breaks and paid training that falls within the defined work period. Paid leave is outside of an on-the-clock study. For a crew, add the eligible labor hours across the included technicians (don't substitute elapsed shift for total labor hours).

State the population clearly. One study might look at the plant's mechanical crew on all shifts (including all scheduled and unscheduled overtime) and exclude contractors. Another study might include contractors, as long as both their actual activities and their eligible hours are captured in the same way. You need to make that decision prior to data collection.

Estimate Wrench Time From Observations

Representative observations with equal selection probabilities support this estimate:

Wrench time estimate = direct-work observations ÷ valid classified observations × 100

With 105 direct observations out of 300 valid classified observations, estimated wrench time is 35%. Sampling provides an estimate of the distribution of time; it doesn't record every single minute of work. The estimate therefore has to take into account both coverage and sampling uncertainty.

If you're sampling shifts at different rates, then simply combining the observations may over-represent one shift. You may need to weight them to reflect the paid time population. For instance, an equal number of observations from a small night crew and a large day crew may not represent the whole plant.

Report any missed/uncertain observations separately. Look to see if the missed observations are concentrated in remote locations, certain shifts, or difficult jobs. Don't just quietly count an unobserved technician as working or idle.

A work-order timer or labor total is insufficient unless the records distinguish direct maintenance from support and delay. Reliable inputs and clear boundaries matter more than whether the calculation is manual or automated.

What Is a Good Wrench Time Percentage?

Where the 35 and 55 Percent Figures Come From

In his January 5, 2022, benchmark discussion, Doc Palmer gives figures of about 35% as typical wrench time and about 55% as best practice. Those are figures from a published practitioner account and should be credited to Palmer rather than presented as some kind of current, representative survey of the industry as a whole.

The August 12, 2015, revision of SMRP Metric 5.6.1 sets a 50–55% target. That target is qualified in the reference by a mature planning environment and a proactive maintenance environment in which the required work is identified well in advance so that it can be prepared for. It's not a target that is expected to be achieved in every crew.

These sources answer quite different questions: what the practitioner reports seeing, and what the dated metric reference suggests as a target. Neither of them establishes that your facility should be expected to achieve that same outcome under a different codebook, work mix, or operating boundary.

Use the wrench time benchmarks to frame the questions around preparation and delays. Saying that a percentage is 'world class' doesn't demonstrate that the actual work was done properly, that it was necessary, or that it resulted in any improvement to equipment performance.

Set a Target Using Comparable Data

Start with your own baseline. Compare the same crews, covered hours, activity rules, and broadly similar work. A geographically dispersed utility has different travel demands from a compact production line. Access requirements, equipment complexity, shift coverage, and the mix of inspections and repairs also affect how time is distributed.

Set a local target around a quantifiable constraint (e.g., reduce parts waiting time following an improvement to kit completeness). Agree on the supporting evidence prior to settling on the target percentage, and a target is far more useful if the team can explain which process change would make it achievable.

100% is inappropriate for a full paid period of work that includes necessary support and breaks. You can have a high result and still have a lot of rework and/or very long jobs. You need to be looking at whether the crew is actually doing useful maintenance in a safe and correct manner rather than just looking at the amount of direct work.

How to Conduct a Wrench Time Study

Explain the purpose to the technicians before collection begins (i.e., to identify the barriers and to improve the working process). Report the results at crew level and invite the technicians to challenge any of the categories or explanations that they find unclear.

Choose the Measurement Method

SMRP identifies work sampling as the method for estimating activity shares. For the crew-level estimate, you take representative random observations. You then go on to look at the recurrent interruptions via focused observation and discussion with the technician. For example, you might follow the handoffs on a delayed job to work out whether it was an incomplete instruction or an unavailable part that was the cause.

A computerized maintenance management system (CMMS) can be used to identify job types and recorded delays. Ensure the activity coding is valid before treating the labor records as direct work measurements.

Table B What Each Measurement Method Can Show

Method

Useful for

Limit to explain

Random work sampling

Estimating how a crew's time is distributed

Needs representative selection and uncertainty analysis

Continuous observation or a day in the life

Understanding task sequence, interruptions, and handoffs

One person's day does not establish a plant average

CMMS labor and activity records

Analyzing recorded assignments, time, and coded delays

Total job labor and open-to-close timestamps are not direct-work measures by themselves

Define the Population and Activity Categories

Write out a study plan which includes the crews, shifts, job types, dates, and eligible paid hours. State how overtime and contractors will be dealt with. Paid training must be included consistently when it occurs within the defined paid period, and any predetermined exclusions must be disclosed.

Pilot Table A with the observers and technicians prior to the main study. Have the observers independently classify the same situations and then go on to discuss the differences.

Distinguish between receiving instructions (that's support) and waiting for instructions (that's code I). Use one mutually exclusive primary activity code and a separate reason field for suspected causes. Freeze the agreed rules before collection begins.

Plan Representative Observations

Select observation times across the full paid period (including shift start and finish). Randomize both the technician and the timing so that each eligible individual's time has the intended chance of being included. A route which invariably goes to the storeroom after break can create a very misleading pattern.

Include the remote areas and the less visible crews in your access plan. Don't just swap out a selected technician for the one who's easiest to track down. Record any missed observations, and if access keeps on being an issue, then review your sampling design.

Normal operations and an outage are two very different work populations. They should be analyzed separately unless the stated purpose and weighting would support a combined estimate. The study coverage and sample size should be chosen in the context of the decision, the work cycle, and the required precision. A fixed number of days will not necessarily give you a representative result.

Record the Study in a Worksheet

One observation is one selected technician's activity at one instant. Record each technician separately, one observation per row in the accompanying editable worksheet. The fields are as follows:

Observation worksheet fields

Field

Entry

Study ID

Identify the study round.

Observer ID

Identify the trained observer.

Anonymous technician ID

Use a consistent anonymous identifier.

Date and time

Record the observation instant.

Crew and shift

Identify the covered group.

Work type

For example, inspection or corrective repair.

Activity code

D, S, P, A, I, or B; valid observations only.

Delay reason

Record the suspected cause separately.

Observation status

Valid, not observed, or uncertain.

Notes

Add context for validation and follow-up.

Use the six Table A codes only for valid observations. Status must be able to differentiate between valid, not observed, and uncertain. Leave the activity code blank where the classification is not resolved. Anonymous identifiers are to be used for checking coverage and for identifying duplicates, not for individual ranking.

Don't interrupt the active work to complete a row. Deal with category ambiguities in a suitable discussion at a later stage and keep the original observation details as they are.

Download the Wrench Time Study Worksheet (Word) to record observations using the activity categories explained above.

Check Sampling Uncertainty and Data Quality

An observed proportion will vary from sample to sample. The National Institute of Standards and Technology (NIST) has a discussion of confidence intervals for a proportion (including the Wilson method). Choose an interval that is appropriate to your study design and also check observer agreement as well as sampling variation.

Sample size planning is a separate exercise. For this example, use the standard normal approximation formula for a proportion with independent random observations, 95% confidence, a margin of error of about 5 percentage points, and an assumed proportion of p = 0.5:

n ≈ 1.96² × 0.5 × 0.5 ÷ 0.05² = 384.16, rounded up to 385

This is not a universal minimum and is by no means a guarantee of precision. Observations within a job or crew can be correlated, which will reduce the amount of information you get from any further observations. Missing observations and unequal sampling all require appropriate analysis.

Get statistical assistance if weighting, clustering, or non-response could have a material impact on the decision. More observations won't fix the underlying systematic problems or the inconsistent coding.

Turn the Findings Into an Action List

Show every activity share with its observation count, its sample coverage, and its uncertainty. Look at the biggest delay categories with the technicians and then rank the reasons that the investigation supports. A parts waiting percentage on its own is not going to tell you whether you have an incorrect stock record or an incomplete job plan.

Assign an owner to each selected change, a completion date, and a verification measure. Allow the change to operate for a sufficient period of time to have an effect on similar work before repeating the study. Use the same definitions and check both the targeted delay and the maintenance results.

How to Improve Wrench Time

Prepare Jobs Before Scheduling Them

A job that's ready to schedule has a clear scope, relevant instructions, the right skills, the parts and tools confirmed, access arrangements in place, and the appropriate safety requirements. The planner will deal with any foreseeable preparation gaps prior to the job reaching the weekly schedule. Scheduling then simply matches up the ready work with the available people and agreed operating windows.

As an example of the type of thing that can go wrong, imagine a pump-seal replacement plan that lists the seal but omits both the gasket and the lifting attachment. The crew spots both omissions on arrival. The planner then checks with the technicians what the correct equipment configuration is, updates the materials list accordingly, and adds the lifting requirement to the plan. The storeroom and tool custodian then confirm availability prior to the next job.

Use technician feedback to maintain the recurring plans. Log incorrect part numbers, missing dimensions, unclear steps, and actual access problems where the planner can make a change. Check the revised plan on the next applicable job. A plan that looks complete in the CMMS doesn't necessarily work at the equipment.

Stage Parts and Tools and Coordinate Access

Kitting should link the job scope to the correct spares and quantities. The storeroom will check that the correct item is identified and available and then stage the kit in the right place for the crew to pull it out when they need it. Make sure that any special tools are both serviceable and available rather than just assuming a shared tool will be free.

Look at the repeated trips first before you go and add a storage location or a delivery service. A bad equipment record needs to be corrected and an incomplete bill of materials (BOM) needs better information. Simply moving inventory closer isn't going to fix either of those issues by itself.

Operations and maintenance should be in agreement as to when the equipment is available and who will confirm it's ready. The access requirements and the safety work required should be clearly defined. A supervisor can confirm that the planned operating window still stands prior to sending the crew.

If the conditions change, then arrange the other ready work in the meantime while the access issue is being resolved. Minimize the time you're waiting for isolation or permits without compromising the time and controls you need to carry them out.

Control Schedule Changes and Waiting for Instructions

Give the crew a clear work assignment, clearly defined priorities, and a named supervisor who can deal with the inevitable competing requests. The technicians need to know where to go if they have an unclear scope or conflicting instruction rather than having to wait between a number of people who could potentially make a decision.

Provide a defined route for legitimate urgent work. Operations will define the impact and timing; maintenance will assess the response; the supervisor will authorize the change and will identify which of the scheduled jobs will be affected. Planning will then update the information and the readiness required for the displaced/replacement job.

Record the reason for each interruption so that the team can tell the difference between genuinely urgent work and requests that could simply be dealt with in the normal planning process. Reliable's piece on schedule compliance looks at how uncontrolled changes can disrupt an otherwise well-prepared schedule.

At the daily coordination meeting, look at the known access conflicts and work out the alternatives that are available. Check the instruction-related waiting after that. Schedule compliance and reactive labor time answer different questions, so don't treat one percentage as the inverse of the other.

Verify Improvements With the Crew

Use Table C to link a finding to an accountable change and a direct check.

Table C From a Finding to a Verified Improvement

Finding

Change and responsible function

Verification

Parts or tools unavailable

Planner and storeroom confirm and stage the job requirements

Sampled parts/tool waiting and kit completeness

Equipment or approvals not ready

Operations and maintenance coordinate access and prerequisites

Readiness at the agreed start and access-related waiting

Waiting for assignment or instructions

Supervisor and planner clarify priorities and job information

Instruction/assignment waiting and plan feedback

Repeated trips or preparation problems

Planner and crew investigate layout, information, and staging

Reason-coded interruptions, with required support preserved

Ask whether the specific delay has been reduced and whether the technicians can in fact carry out the required work safely and to the required standard. Keep the required support in view. Before you go ahead and credit a higher proportion to the intervention, you need to check that there hasn't been a change in coding, easier access, or a different work mix.

Recovered time is an opportunity to do the work that needs doing. It doesn't equate to a reduction in payroll or justify a reduction in staff. You need to check what the crew actually did with that time and whether the improvement is sustained under similar conditions.

Wrench Time Improvement Example

Compare Two Studies of the Same Crew

This is a hypothetical scenario of 10 technicians working 40 paid hours each (i.e., 400 paid crew hours per week) with no absences and no full day of training. Each study has 1,000 valid observations with equal selection probabilities over comparable covered periods. That number in itself makes no claim as to adequate statistical precision.

Kitting, access coordination, and clearer assignments are the interventions being looked at. Table D shows a potential outcome (it's not a measured Reliable client outcome and doesn't prove that those changes caused it).

Table D Hypothetical Observations Before and After Changes

Activity

Baseline count

Follow-up count

Baseline share

Follow-up share

D Direct maintenance work

350

450

35%

45%

S Required supporting activity

250

250

25%

25%

P Waiting for parts or tools

150

100

15%

10%

A Waiting for access or readiness

100

70

10%

7%

I Waiting for instructions

50

30

5%

3%

B Paid breaks and personal time

100

100

10%

10%

Total valid classified observations

1000

1000

100%

100%

Convert the Change Into Estimated Work Hours

Apply each estimated direct-work share to the same paid crew-hours:

Baseline: 400 × 35% = 140 estimated direct-work hours

Follow-up: 400 × 45% = 180 estimated direct-work hours

The difference is 40 estimated direct-work hours (a 10-percentage-point increase in wrench time and 28.6% more direct-work hours on a 140-hour baseline: 40 ÷ 140 × 100).

Paid Time Distribution
Figure 1: Hypothetical distribution of paid crew time before and after the changes. Direct maintenance goes up from 35% to 45% (support and paid breaks are the same). 1,000 valid observations per round. Based on the hypothetical example in Table D.

Required support is still 25%, and paid breaks and personal time are still 10%. The estimated capacity change doesn't establish any completed work, work quality, payroll savings, or reduced downtime. Those are all outcomes that would require separate evidence. It doesn't represent the output of one additional technician either, as the paid week for that person would be a mixture of direct work and other activities.

How to Use Wrench Time With Other Maintenance Metrics

Read wrench time in conjunction with the measures that test what the maintenance team actually delivers. Schedule compliance looks at whether the work that was agreed was completed as scheduled. Backlog age and risk tell you whether the critical work is still sitting in the backlog. Rework and repeat failures are the measures of repair quality, and equipment availability or failure-related downtime are the measures of operational results.

Torbjörn Idhammar's critique of the limitations of wrench time as a measure of performance directly challenges the notion that any visible activity will in fact improve reliability. That's a useful check on any program you might have to increase the percentage.

Keep denominators visible. 60% schedule compliance does not mean that 40% of crew-hours were reactive. A job-count measure, a scheduled-hours measure, and a paid-time share are all measures of different things. Completed job counts can go up simply because the crew has done more small jobs rather than more useful work.

For the next improvement, define the activity categories, establish a representative baseline, and remove one verified source of delay. Remeasure under comparable conditions with work quality and equipment results checked. Continue the change when the evidence shows it is helping the crew to do the required maintenance and investigate further when the percentage has improved but the outcomes have not.

Frequently Asked Questions About Wrench Time

Is Wrench Time the Same as Productivity?

No. Wrench time describes the allocation of paid time under a defined activity convention. Productivity also requires evidence of useful output, and maintenance effectiveness requires work quality and equipment results. A technician could well spend a lot of time on direct maintenance simply because the same repair keeps on failing, and that wouldn't be an example of improvement.

Can a CMMS Calculate Wrench Time Automatically?

Only with appropriate activity distinctions and reliable data. Job timestamps and total charged labor are insufficient on their own. Clark and Palmer's account of recorded craft utilization is very clear in that Gwinnett County didn't measure wrench time. Any automated estimate must be validated against the stated population, the stated categories, and the stated method of measurement prior to being used for any decision.

Does Troubleshooting Count as Wrench Time?

Yes, that's the convention we've adopted under this guide. Active diagnosis includes interpreting readings, examining drawings, and testing possible causes of a fault. Waiting for information or instructions falls into a different category. Requiring a tool to be in the technician's hand would exclude legitimate forms of direct maintenance and could skew the comparisons between different trades and types of jobs.

Should Safety Meetings and LOTO Count as Wrench Time?

In this guide, safety meetings and LOTO are still paid time and are coded as necessary support. Other conventions may treat specific job-related safety activities as wrench time. Record the rule and apply it consistently. The required controls remain required irrespective of which category the observation falls into; changing the code doesn't remove the need for the controls.

How Often Should a Wrench Time Study Be Repeated?

Repeat it after an improvement has been implemented and has had time to impact a comparable operating period. The timing should reflect the decision, the work cycle, and the required degree of precision. You should be comparing similar conditions and reporting any material changes. There is no one monthly or quarterly schedule that will make your study for a particular facility representative or useful.

Can Wrench Time Reach 100 Percent?

A full paid work period encompasses all the necessary support, breaks, and other activities, so 100% is an inappropriate target. A very high figure can be achieved with a very short observation window or with overly broad coding. That figure on its own doesn't demonstrate good maintenance, safe operation, high work quality, or improved equipment reliability.

Related reading

Sources

1. SMRP Metric 5.6.1 Wrench Time. Revised August 12, 2015. Historical reference for definitions, formulas, and the qualified 50–55% target.

2. Doc Palmer, Why Wrench Time Can Be a Terrible Metric. Plant Services, January 5, 2022. Practitioner benchmarks and activity conventions.

3. Matthew Clark and Doc Palmer, Righting the Maintenance Planning Ship. Plant Services, August 14, 2019. Recorded craft utilization distinguished from wrench time.

4. Torbjörn Idhammar, 6 Reasons to Kill Wrench Time Studies! IDCON. Critical perspective on activity, useful work, and reliability.

5. NIST/SEMATECH e-Handbook, 7.2.4.1. Confidence intervals. Confidence intervals for proportions, including the Wilson method.

6. OpenStax, Statistics, 8.3 A Population Proportion. Standard normal-approximation formula for planning sample size when estimating a proportion.

7. OSHA, 29 CFR 1910.147, The Control of Hazardous Energy. Requirements for covered servicing and maintenance.